全国造价员桩基础工程量清单计价例题1
按表2-13方法,套用计价定额,计算每个分部分项清单项目的综合单价如下表:
分部分项工程量清单项目综合单价分析表表2-14
序号项目编码或
定额编号项目
名称计量单位工程数量人工费材料费机械费企业管理费利润综合
单价
1010201001001预制桩根1263.491028.86801.38127.7982.502306.72
2-11压桩m34.4852.5321.15382.4052.1934.79543.06
2-15送桩m30.4327.290.5047.206.544.3665.89
4-319制桩m34.547174.26988.053.4727.3318.221261.28
4-415H运桩m34.4829.4119.21318.3141.7327.83436.49
2010201001002预制桩根1293.411028.861016.18157.16104.782600.39
2-11H压试桩m34.4878.8021.15573.6078.2952.19804.03
2-15H送试桩m30.43210.940.5070.809.816.5498.59
4-319制桩m34.547174.26988.053.4727.3318.221261.28
4-415H运桩m34.4829.4119.21318.3141.7327.83436.49
3010201002001接桩个17.8226.8310.172.161.4448.42
2-18角钢kg9.397.8226.8310.172.161.4448.42
4010201002002接试桩个111.7226.8315.263.242.1659.21
2-18H角钢kg9.3911.7226.8315.263.242.1659.21
以普通压桩子目各费计算说明表中各数值的计算方法如下:
人工费=4.48×10.66×(1+10%风险)=52.53元/根
材料费=4.48×4.629×(1+2%风险)=21.15元/根
机械费=4.48×81.293×(1+5%风险)=382.40元/根
企业管理费=(52.53+382.40)×12%=52.19元/根
利润=(52.53+382.40)×8%=34.79元/根
现场汽车运桩在500m以内,定额按说明乘系数0.85;施工方案选定的履带吊,定额机械费换算为:94.11+(454.25-787.64)×0.0435=79.61元/m3
运桩距离超过200m,如现场场地不适宜用汽车运输的,按施工方案采用的运输机械内容组价计算;场地修整内容列入措施费项目计算。
按照确定的综合单价,填报分部分项工程量清单计价表:
分部分项工程量清单计价表表2-15
工程名称:XXX工程第X页共X页
序号项目编码项目名称计量单位工程
数量金额(元)
综合
单价合价
1010201001001预制钢筋混凝土桩:二级土;单桩长度14+14m,桩截面400×400;C40混凝土制作;现场运输≥350m;桩顶标高-2.5m,自然地坪标高-0.3m根952306.72212138
2010201001002预制钢筋混凝土桩:试桩;二级土;单桩长度14+14m,桩截面400×400;C40混凝土制作;现场运输≥350m;桩顶标高-2.5m,自然地坪标高-0.3m根52600.3913002
3010201002001普通方桩接桩:4L75×6焊接,
长340mm个9548.424600
4010201002002试桩方桩接桩:4L75×6焊接,
长340mm个559.21296
本页小计230036
措施项目计价:
桩制作模板未考虑现场地模不同调整因素,套用4-238定额计价,
人工费=454.72×58.5×(1+10%)=29261元
材料费=454.72×50.491×(1+2%)=23418元
机械费=454.72×5.502×(1+5%)=2387元
企业管理费=(29261+2387)×12%=3798元
利润=(29261+2387)×8%=2532元
合计=61396元
大型机械进退场及安拆费套用定额附录(二)相应价格计算,其中工料机价格标准同分部分项工程计价,按照施工取费定额,不计企管费和利润:
3000KN压桩机安拆及退场费(编号2011+3015)
人工费=[1872+1248×(1+40%)]×(1+10%)=3981元
材料费=[26.47+66.1×(1+40%)]×(1+2%)=121元
机械费=[8604.35+15711.5×(1+40%)]×(1+5%)=32130元
小计=36232元
式中:40%为机械回程费用,按定额取定比例计算,定额台次单价计价内已列入,本例按定额架线费计算基数及比例分解,列入相应费用内计算。
15t履带式起重机退场费(编号3005,其中架线费不考虑价格调整)
人工费=312×(1+25%)×(1+10%)=429元
材料费=173.54×(1+25%)×(1+2%)=221元
机械费=312×(1+25%)×(1+5%)=410元
架线费=315×(1+25%)=394元
小计=1454元/台×2台=2908原
大型机械进退场及安拆费合计:39140元措施项目计价列表如下:
措施项目清单计价表表2-16
工程名称:XXX工程第X页共X页
序号项目名称金额(元)
1模板工程61396
2大型机械进出场及安拆39140
3合计100536把造价员站点加入收藏夹
分部分项工程量清单项目综合单价分析表表2-14
序号项目编码或
定额编号项目
名称计量单位工程数量人工费材料费机械费企业管理费利润综合
单价
1010201001001预制桩根1263.491028.86801.38127.7982.502306.72
2-11压桩m34.4852.5321.15382.4052.1934.79543.06
2-15送桩m30.4327.290.5047.206.544.3665.89
4-319制桩m34.547174.26988.053.4727.3318.221261.28
4-415H运桩m34.4829.4119.21318.3141.7327.83436.49
2010201001002预制桩根1293.411028.861016.18157.16104.782600.39
2-11H压试桩m34.4878.8021.15573.6078.2952.19804.03
2-15H送试桩m30.43210.940.5070.809.816.5498.59
4-319制桩m34.547174.26988.053.4727.3318.221261.28
4-415H运桩m34.4829.4119.21318.3141.7327.83436.49
3010201002001接桩个17.8226.8310.172.161.4448.42
2-18角钢kg9.397.8226.8310.172.161.4448.42
4010201002002接试桩个111.7226.8315.263.242.1659.21
2-18H角钢kg9.3911.7226.8315.263.242.1659.21
以普通压桩子目各费计算说明表中各数值的计算方法如下:
人工费=4.48×10.66×(1+10%风险)=52.53元/根
材料费=4.48×4.629×(1+2%风险)=21.15元/根
机械费=4.48×81.293×(1+5%风险)=382.40元/根
企业管理费=(52.53+382.40)×12%=52.19元/根
利润=(52.53+382.40)×8%=34.79元/根
现场汽车运桩在500m以内,定额按说明乘系数0.85;施工方案选定的履带吊,定额机械费换算为:94.11+(454.25-787.64)×0.0435=79.61元/m3
运桩距离超过200m,如现场场地不适宜用汽车运输的,按施工方案采用的运输机械内容组价计算;场地修整内容列入措施费项目计算。
按照确定的综合单价,填报分部分项工程量清单计价表:
分部分项工程量清单计价表表2-15
工程名称:XXX工程第X页共X页
序号项目编码项目名称计量单位工程
数量金额(元)
综合
单价合价
1010201001001预制钢筋混凝土桩:二级土;单桩长度14+14m,桩截面400×400;C40混凝土制作;现场运输≥350m;桩顶标高-2.5m,自然地坪标高-0.3m根952306.72212138
2010201001002预制钢筋混凝土桩:试桩;二级土;单桩长度14+14m,桩截面400×400;C40混凝土制作;现场运输≥350m;桩顶标高-2.5m,自然地坪标高-0.3m根52600.3913002
3010201002001普通方桩接桩:4L75×6焊接,
长340mm个9548.424600
4010201002002试桩方桩接桩:4L75×6焊接,
长340mm个559.21296
本页小计230036
措施项目计价:
桩制作模板未考虑现场地模不同调整因素,套用4-238定额计价,
人工费=454.72×58.5×(1+10%)=29261元
材料费=454.72×50.491×(1+2%)=23418元
机械费=454.72×5.502×(1+5%)=2387元
企业管理费=(29261+2387)×12%=3798元
利润=(29261+2387)×8%=2532元
合计=61396元
大型机械进退场及安拆费套用定额附录(二)相应价格计算,其中工料机价格标准同分部分项工程计价,按照施工取费定额,不计企管费和利润:
3000KN压桩机安拆及退场费(编号2011+3015)
人工费=[1872+1248×(1+40%)]×(1+10%)=3981元
材料费=[26.47+66.1×(1+40%)]×(1+2%)=121元
机械费=[8604.35+15711.5×(1+40%)]×(1+5%)=32130元
小计=36232元
式中:40%为机械回程费用,按定额取定比例计算,定额台次单价计价内已列入,本例按定额架线费计算基数及比例分解,列入相应费用内计算。
15t履带式起重机退场费(编号3005,其中架线费不考虑价格调整)
人工费=312×(1+25%)×(1+10%)=429元
材料费=173.54×(1+25%)×(1+2%)=221元
机械费=312×(1+25%)×(1+5%)=410元
架线费=315×(1+25%)=394元
小计=1454元/台×2台=2908原
大型机械进退场及安拆费合计:39140元措施项目计价列表如下:
措施项目清单计价表表2-16
工程名称:XXX工程第X页共X页
序号项目名称金额(元)
1模板工程61396
2大型机械进出场及安拆39140